Thursday, July 28, 2011

U.S. 60 milling, paving starts Friday

Milling and paving work in Livingston County along U.S. 60 between Marion and Smithland and Ky. 967 is under way this week. The work along U.S. 60 starts just east of Burna and runs to the Livingston-Crittenden County line just east of Salem.

Milling and paving along Ky. 967 runs from the intersection with U.S. 60 near Smithland City Hall northward to Court Street. This runs at the rear of the new Livingston County Judicial Center.

The milling and paving schedule for these projects is as follows:
  • Friday and Saturday: Cut back shoulders on U.S. 60 and remove pavement markers.
  • Monday: Milling along both projects.
  • Tuesday: Start paving operations on Ky. 967 and then moving to U.S. 60.
Motorists should be alert for road crews working along the roadway where traffic will be restricted to one lane. Paving along these projects is expected to take about a week, weather permitting.