Tuesday, October 28, 2014

Contractor continues demolition of bridge

The contractor working to demolish the old Ledbetter Bridge at Paducah is continuing efforts to tear down and remove the remains of the once proud structure.

Today, a demolition crew worked to remove the final remnants of three west approach spans that collapsed due to land movement back in June. A trackhoe mounted with a shear was cutting up remaining pieces of steel from the approaches on the McCracken County side of the Tennessee River. Another trackhoe with a large jackhammer attached was busy breaking up two huge concrete piers that were brought down by the massive movement of land along the McCracken County shoreline.

The contractor has a goal of having the site cleared by Dec. 1. However, when the last steel truss section over the Tennessee River main navigation channel was detonated Oct. 1, the blast rocked over the piers that held it up, causing damage to the concrete structures. The contractor had planned to place a platform on the piers, drill them for placement of explosives, then bring them down with a series of controlled detonations. But, cracks left in the piers raised safety questions about the drilling process.

Kentucky Transportation Cabinet engineers and the company are continuing to work on several viable options for removing the in-water piers, but it may be several weeks before a plan is fully developed and approved. Meanwhile, the contractor has continued conventional demolition of the approach spans.
The contractor is required to give the U.S. Coast Guard 15 days advance notice before demolition can start on the river-based piers.

The old Ledbetter Bridge went into service in 1931. In January 2012 it had to be restricted to a 3-ton load limit.

Completion of the new U.S. 60 Tennessee River Bridge at Ledbetter was expedited and traffic flow moved to the new structure on July 31, 2013.