Prep and paving operations are planned at the following dates and locations:
Locations:
- Ky. 120/Marion-Shady Grove Road: Starting mile point: 0.000, ending mile point: 0.340
- Ky. 981/Old Salem Road: starting mile point: 0.000, ending mile point: 0.485
- Ky. 2132/Sisco Chapel Road: Starting mile point: 0.000, nding mile point: 2.600
- Today: Cut back edges on Ky. 2132 and Ky. 981
- Wednesday: Start, complete paving operations on Ky. 2132
- Oct. 11: Start, complete paving operations on Ky. 981
- Oct. 14: Milling along Ky. 120
- Oct. 15: Start, complete paving operations on Ky. 120